To take the PRINCE2 Practitioner examination you must provide proof of having passed one of the following:
- IPMA Level A® (Certified Projects Director)
- Certified Associate in Project Management (CAPM)
- IPMA Level D® (Certified Project Management Associate)
- IPMA Level C® (Certified Project Manager)
- PRINCE2 Foundation (or higher) - this only applies to certificates obtained after 1 January 2009
- Project Professional Qualification (PPQ)
- IPMA Level B® (Certified Senior Project Manager)
NEW QUESTION 48
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The Health and Safety Training Project has been divided into four stages. The executive considers this project to be a compulsory project and has advised the project manager that it is not necessary to produce the project initiation documentation. This would mean that the project would consist of three delivery stages.
How well does this apply the 'manage by stages' principle?
- A. It applies it poorly, because solid foundations should be established for every project.
- B. It applies it poorly, because the stages should be shorter to provide more control to the project board.
- C. It applies it well, because the justification for delivering the project is already understood.
- D. It applies it well, because the project management method should be tailored to the project.
Answer: A
NEW QUESTION 49
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule.
The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the E500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Plan prerequisites section?
- A. Add 'Engineering team must be made available for photos'.
- B. Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a prerequisite for stage
3. - C. Delete entry 4 because the customer list is a deliverable of stage 2, not a prerequisite for stage 3.
- D. Delete entry 2 because these are project benefits not prerequisites of the stage.
- E. Add 'Compliance with the Data Protection Act'.
Answer: C,D
NEW QUESTION 50
Scenario
Additional Information
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed user assurance for this project?
- A. Retain because their divisions will be the major users of the outsourced services and they can provide the user perspective on the impact of any proposed changes.
- B. Retain because selecting only one of them may cause unnecessary conflict.
- C. Retain because they are able to help identify stakeholders and their communication requirements.
- D. Retain because they are both very positive about outsourcing the selected business functions.
- E. Remove because neither of these individuals are from the business functions to be outsourced.
Answer: A,C
NEW QUESTION 51
The delivery of the pilot courses has been split into two separate products: 'planned pilot courses' and
'delivered pilot courses'. 'Planned pilot courses' will be produced during stage 3, and the 'delivered pilot
courses' will take place during stage 4. This will allow the project board to approve the plan for the pilot courses
before the resources are committed to delivering the pilot courses.
Why is this an appropriate application of the plans theme to control the project?
- A. Because the pilot courses have been broken down into two separate products.
- B. Because the delivery steps to create the pilot courses have been aligned to the management stages.
- C. Because a PRINCE2 project should focus on the quality of the products being delivered.
- D. Because the project board should ensure that lessons from one stage are applied to the next stage.
Answer: B
NEW QUESTION 52
Which 2 statements should be recorded under the Reasons heading?
- A. The Marketing department believes that the effect of a good company image, portrayed by a successful calendar, will last into a second year.
- B. MNO Manufacturing is experiencing a fall in orders due in part to the increased marketing activities of its competitors.
- C. 10% of customers have not re-ordered in this financial year.
- D. 1,500 orders are expected, each with an average profit of £2k.
- E. The Marketing department believes that sending a promotional calendar to current and prospective customers will increase orders by at least 10%.
Answer: B,C
NEW QUESTION 53
The Health and Safety Training Project has been divided into four stages. The executive considers this project to be a compulsory project and has advised the project manager that it is not necessary to produce the project initiation documentation. This would mean that the project would consist of three delivery stages.
How well does this apply the 'manage by stages' principle?
- A. It applies it poorly, because solid foundations should be established for every project.
- B. It applies it poorly, because the stages should be shorter to provide more control to the project board.
- C. It applies it well, because the justification for delivering the project is already understood.
- D. It applies it well, because the project management method should be tailored to the project.
Answer: A
Explanation:
Explanation
NEW QUESTION 54
Scenario
Additional Information
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed business assurance for this project?
- A. Add Outcome Consultants' because they carried out the feasibility study.
- B. Retain because he is familiar with the Ministry of Food Hygiene business strategy, the business level risk assessment and the Business Case standards.
- C. Replace with 'Project Manager' because this is a simple project that does not require additional business assurance.
- D. Add 'Director of Finance Division' because she is responsible for checking that any supplier and contractor payments are authorized.
- E. Remove because he will be impacted by the project and therefore represents a user.
Answer: B,D
NEW QUESTION 55
During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?
- A. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.
- B. The Executive needs to seek formal approval from corporate management to implement this change.
- C. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.
- D. The tolerances stated in the Project Plan CANNOT be changed.
Answer: B
NEW QUESTION 56
Which statement applies to the Introduction section?
- A. Delete entry 3 because it is the Project Manager's responsibility to implement the Quality Management Strategy.
- B. Delete entry 1 because the project approach is defined in the Project Brief.
- C. Move entry 3 to the Roles and responsibilities section because this is a quality responsibility.
- D. Delete entry 2 because this is the Project Manager's responsibility.
Answer: C
Explanation:
Explanation/Reference:
Question Set 1
NEW QUESTION 57
MANAGING PRODUCT DELIVERY
The team manager for the production of the 'marketing materials' has identified that they will not be ready
within the timescale agreed in the work package. The team manager has sufficient tolerance to take corrective
action. As a result, additional resources have been assigned to this work package.
Which theme is being applied?
- A. Change
- B. Organization
- C. Risk
- D. Progress
Answer: C
NEW QUESTION 58
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him.
They promote existing training courses to other training companies and existing customers.
End of the additional information.
The delivery of the pilot courses has been split into two separate products: 'planned pilot courses' and
'delivered pilot courses'. 'Planned pilot courses' will be produced during stage 3, and the 'delivered pilot courses' will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses.
Why is this an appropriate application of the plans theme to control the project?
- A. Because the pilot courses have been broken down into two separate products.
- B. Because the delivery steps to create the pilot courses have been aligned to the management stages.
- C. Because a PRINCE2 project should focus on the quality of the products being delivered.
- D. Because the project board should ensure that lessons from one stage are applied to the next stage.
Answer: B
NEW QUESTION 59
STARTING UP A PROJECT
Here are three actions carried out by the project manager during the 'starting up a project' process.
As part of which activity (A-F) should each action be carried out?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Answer:
Explanation:
Explanation
NEW QUESTION 60
HOTSPOT
The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Hot Area:
Answer:
Explanation:
Explanation/Reference:
NEW QUESTION 61
M1ich statement is an appropriate entry for the outline Business Case heading within the Project Brief?
- A. The project should be split into four management stages.
- B. External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits.
- C. 10 year service contract should be agreed with the selected service provider.
- D. The project will run for two years and the benefits will be realized over 1a years.
Answer: D
NEW QUESTION 62
The senior user is concerned that the trainers' limited availability could delay their accreditation. This was discussed during the 'starting up a project' process, but during the 'initiating a project' process the project manager notices that it has not been recorded.
Which action should the project manager take FIRST?
- A. Raise an exception report to manage the impact that any such delay would have on the project plan.
- B. Raise an issue report so that the trainers' time can be allocated to the accreditation activities.
- C. Add the information to the risk register so that it can be evaluated and an action decided.
- D. Add appropriate activities to the project plan to manage the concern and avoid any adverse impact.
Answer: D
NEW QUESTION 63
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Monitoring and control section?
- A. No change to entry 12 because this describes how the Project Board will control the stage. ~
- B. Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not the Stage Plan.
- C. Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is produced at the end of each stage to identify any variations between planned status, reported status and actual status of the stage's products.
- D. Delete entry 13 because this is part of the Controlling a Stage process.
- E. Move entd12 because the Highlight Reports are deliverables of this stage and should be shown under Product descriptions.
Answer: A,B
NEW QUESTION 64
Scenario
Additional Information
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago.
She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed Senior User for this project?
- A. Retain because he will be providing support to the Information Technology and Facilities teams during the project.
- B. Remove because he has no authority to commit user resources.
- C. Replace with 'Director of Research and Development' because she deals with both the Information Technology and the Facilities Divisions and can make sure her division's needs are specified.
- D. Add 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome.
- E. Retain because he provides the outsourcing resources required to support the project.
Answer: B,C
NEW QUESTION 65
Which of the following statements are True:
1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or
organization.
2. Quality planning is about defining products required of the project with their respective quality criteria,
methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out quality inspections
4. Quality assurance ensures that quality methods are being correctly followed.
- A. 1, 3 & 4
- B. 2, 3 & 4
- C. 1, 2 & 3
- D. 1, 2 & 4
Answer: C
NEW QUESTION 66
The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.
Which 2 actions should the Team Manager take to check that the completed products have been approved as required?
- A. Check the Work Package to ascertain who should approve the completed Work Package.
- B. Check the Configuration Management Strategy for product handover procedures.
- C. Check the Product Descriptions to ascertain who should have approved the products.
- D. Check the Product Descriptions for the quality method required.
- E. Check the approval records as required in the Work Package.
Answer: C,E
NEW QUESTION 67
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for
this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are
being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago
the professional photographer produced the photo session schedule based on the operational staff schedule.
The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the E500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Monitoring and control section?
- A. Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not the Stage
Plan. - B. Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is produced at the end of
each stage to identify any variations between planned status, reported status and actual status of the
stage's products. - C. Move entry 12 because the Highlight Reports are deliverables of this stage and should be shown under
Product descriptions. - D. Delete entry 13 because this is part of the Controlling a Stage process.
- E. No change to entry 12 because this describes how the Project Board will control the stage.
Answer: A,E
NEW QUESTION 68
Scenario
Additional Information
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed business assurance for this project?
- A. Add Outcome Consultants' because they carried out the feasibility study.
- B. Retain because he is familiar with the Ministry of Food Hygiene business strategy, the business level risk assessment and the Business Case standards.
- C. Replace with 'Project Manager' because this is a simple project that does not require additional business assurance.
- D. Add 'Director of Finance Division' because she is responsible for checking that any supplier and contractor payments are authorized.
- E. Remove because he will be impacted by the project and therefore represents a user.
Answer: B,D
NEW QUESTION 69
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
- Design for each month - correctly showing at public holidays and new company logo - Selected photographs- 12 professionally-produced photographs, showing different
members of staff - Selected paper and selected envelope - for printing and mailing the calendar - Chosen label design - a competition to design a label will be held as part of this
project - List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
- Create the customer fast using information from the Accounts and Marketing
---- --
departments Confirm compliance with the Data Protection Legislation Create a design for each month - this will be done by the internal creative team Select and appoint a professional photographer Gather photograph design ideas from previous project and agree photographic session schedule Prepare a production cost forecast Select paper and envelope.
Stage 3 will include the activities to:
---
Produce and select tie professionally-taken photographs Hold the label design competition and choose the label design Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be (GBP)20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +(GBP)6,000 / -(GBP)6,000. A change budget of (GBP)500 has been allocated but there is no risk budget.
During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?
- A. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.
- B. The Executive needs to seek formal approval from corporate management to implement this change.
- C. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.
- D. The tolerances stated in the Project Plan CANNOT be changed.
Answer: B
Explanation:
Project Scenario
NEW QUESTION 70
......
PRINCE2 PRINCE2-Practitioner Study Guide Archives : https://protechtraining.actualtestsit.com/PRINCE2/PRINCE2-Practitioner-exam-prep-dumps.html